Viviana Power Tech: profit up 2.7 times in FY26, but cash flow and promoter dealings need a closer look
Viviana Power Tech grew its profit about 2.7 times in FY26 and has a ₹1,312 crore order book. But in three years it has reported ₹74 crore of profit (standalone) and generated about minus ₹5 crore of cash from operations. This article shows what is working, what is not, and what to check before you buy.
Viviana Power Tech (NSE: VIVIANA) - Share price: ₹774.5 (1 October 2026 close, the last trading day; 2 October was a market holiday) - Market cap: ₹784 crore - P/E: 14.2 (peers: Transrail Lighting 15.3, Power Mech 20.0, Kalpataru Projects 20.8, Skipper 26.3) - Price to book value: about 6.9 (the book value is ₹113 per share) - ROCE: 50.7%, return on equity: 57.2%. Both show how much profit the company makes from the money invested in it. - 52-week range: ₹565 to ₹1,162. The price is 33% below the high and 37% above the low.
What the company does
Viviana Power Tech was incorporated in 2014 in Vadodara, Gujarat. Its first order was worth ₹21 lakh. It builds power lines, substations and underground cables up to 400 kV, on a "turnkey" basis. That means it designs, buys, builds and hands over a working project. The trade calls this EPC (engineering, procurement and construction).
Most of its recent orders come from state-owned power companies in Gujarat: DGVCL, PGVCL, MGVCL and the transmission company GETCO. Management also names private utilities and renewable-energy developers as customers.
It has three business lines: - Power transmission and distribution work. This is the main revenue earner. Its order book is above ₹800 crore. (An order book is the value of work already won but not yet done.) - Battery energy storage (BESS). These are large batteries that store electricity for the power grid. Two projects worth about ₹500 crore in total, one in Gujarat and one in Rajasthan. Both still wait for approvals, so this part of the order book cannot be executed yet. - Transformer manufacturing. New. A leased plant that makes transformers up to 20 MVA was inaugurated on 21 September 2026. A larger own factory is planned.
The stock listed on NSE Emerge (the small-company platform) in September 2022. It moved to the NSE main board on 2 June 2026. It is no longer a recent IPO, so this article looks at the business and not at the issue.
How big is the market?
Management does not give a market size. The government gives investment plans instead.
- Transmission. The Central Electricity Authority's national plan sees a ₹9.15 lakh crore investment opportunity in power transmission by 2032. It includes about 190,000 circuit km of new lines over the next decade and 47 GW of battery storage (Business Today, 15 October 2024). - Distribution. The Revamped Distribution Sector Scheme has a total cost of ₹3,03,758 crore. The Centre's own share is about ₹97,631 crore. About ₹30,700 crore had been released by August 2025. The deadline moved from March 2026 to March 2028. The FY27 budget set aside about ₹18,000 crore for it.
These are plans for the whole country. They are not Viviana's share. Viviana's FY26 consolidated revenue was ₹531 crore, a very small slice. But the demand is large and government-backed, which is why order books in this sector have grown.
The numbers
₹ crore FY23 FY24 FY25 FY26 --------------- Sales 36 66 188 502 Operating profit 5 12 26 71 Operating margin 14% 18% 14% 14% Net profit 3 7 17 50
These are standalone figures from screener.in. The company reports on a consolidated basis, which adds its subsidiaries. For FY26 that gives revenue of ₹531.3 crore (up 143%), EBITDA of ₹75.9 crore, and net profit of ₹52.7 crore (up 167%, a margin of 9.9%). The two bases differ a little, so do not compare them line by line.
Sales grew fast, from ₹36 crore to ₹502 crore in three years. But look at when the sales arrive:
₹ crore Jun 2025 Sep 2025 Dec 2025 Mar 2026 Jun 2026 ------------------ Sales 20.8 48.6 113.6 318.7 71.9 Operating margin 16.8% 16.9% 14.8% 13.5% 16.1% Net profit 2.1 4.8 11.1 32.2 6.9
The March 2026 quarter alone made 63% of the year's sales. The company records revenue as different stages of a project are completed, and many of these stages are completed in the last quarter. This makes any single quarter a poor guide.
Did management keep its promises?
This is the key test. These are the targets management gave on earlier calls and what happened.
Said when What management said What happened Result ------------ Dec 2025 call FY26 revenue of about ₹550 to 560 crore (without BESS) ₹531 crore consolidated Slightly missed (3 to 5% short) Dec 2025 call December quarter revenue above ₹100 crore ₹113.6 crore Met Dec 2025 call Move to the NSE main board "soon" Listed on the main board on 2 June 2026 Met Dec 2025 call New orders of ₹500 to 600 crore in the first half of FY27 About ₹251 crore of confirmed orders from July to August. A further ₹466 crore is "lowest bidder" and not yet awarded. In progress, not yet met Jun 2026 presentation FY27 revenue of ₹875 to 925 crore August call: ₹875 to 910 crore Top end trimmed slightly Jun 2026 presentation A real-estate arm, Viviana Life Spaces, as a "collateral engine" for loans Two months later the real-estate arm was sold out of the listed company (completed 17 August 2026). Promoter-owned, it still supplies collateral. Plan reversed
Management delivered on the listing and on the December quarter. It missed FY26 revenue by a small margin. It also changed its plan for the real-estate arm within two months.
The first quarter of FY27 brought ₹71.9 crore. That is about 8% of the low end of the full-year target. Last year the first quarter was 4% of the full year, so the pattern repeats.
Are margins and capacity stable?
Margins are stable, not expanding. Operating margin (the share of sales left after running costs) has stayed between 13.5% and 17% in each of the last five quarters. For FY27, management guides to a profit-after-tax margin of about 9% to 9.5%. FY26 was 10%. So the plan is for stable to slightly lower margins.
Management says that winning larger projects worth ₹1,000 to 2,000 crore could reduce its profit margin. It says it will hold current profitability for four to five years. Nothing in the filings shows how.
Capacity is being added in manufacturing: - A leased transformer plant (up to 20 MVA) opened on 21 September 2026. - A larger own factory is planned in Gujarat. Phase 1 costs about ₹90 crore, of which about ₹10 crore falls in FY27 and most in FY28. It would make transformers up to 132 kV and 63 MVA, with later phases up to 400 kV. Production is expected by the end of FY28. - The company's earlier transformer arm held approvals only up to 500 kVA. Larger sizes need new approvals from the buyers. This will take time.
Outlook and guidance (management's own forward-looking statements)
These are management's targets, not facts and not promises.
- FY27: revenue of ₹875 to 910 crore, profit-after-tax margin of about 9 to 9.5%. At 9 to 9.5% on ₹875 to 910 crore, profit would be about ₹79 to 87 crore. If the target is met, investors at today's market cap of ₹784 crore would be paying about 9 to 10 times that expected FY27 profit. - FY28 (June presentation): consolidated revenue of ₹1,225 to 1,300 crore, margin of 9 to 10%. - FY30: revenue above ₹2,000 crore, profit above ₹200 crore, margin of 10 to 12%. Power transmission and distribution work ₹1,500 crore. Transformers ₹400 to 600 crore. - FY32: power equipment revenue of ₹1,000 to 1,200 crore and profit of ₹100 crore. - Debt: keep debt to equity between 1.0 and 1.5 times. - Orders: order book ₹1,312.5 crore in August 2026 (₹800 crore+ in power work, about ₹500 crore in storage that still awaits approvals). Bids under evaluation above ₹1,400 crore. Active tenders above ₹2,600 crore, mostly in Gujarat and Haryana. Viviana is expected to receive a ₹100 crore order from DGVCL after being named the lowest bidder. ("Lowest bidder", or L1, means it offered the lowest price in a tender but the contract is not yet signed.) New order inflow of ₹500 to 600 crore is targeted for the first half of FY27. - Battery storage: 165 MW / 330 MWh in total, with ₹59.4 crore of government support, 75% term debt and about ₹60 crore of the company's own money. Management says that completing two or three such projects would allow Viviana to bid for much larger projects worth ₹1,000 to 5,000 crore. Those bids need a net worth of ₹250 to 500 crore (June presentation). Viviana's is ₹114 crore. - Working capital: bank limits (the credit a bank allows the company to use) above ₹150 crore, rising above ₹250 crore (December 2025 call).
Recent confirmed orders (company filings):
Date Client Value (₹ crore) --------- 7 July DGVCL 41.5 9 July PGVCL 71.4 22 July PGVCL (several) 128.3 27 August GETCO 9.7
The point to remember Viviana shows strong profit on paper, but the cash has not followed yet. Check cash flow before you check the P/E.
Cash and debt: the weak spot
₹ crore FY24 FY25 FY26 ------------ Net worth (equity plus reserves) 25 61 114 Borrowings 17 30 92 Other liabilities 11 95 349 Operating cash flow -3 -3 1 Debtor days 153 232 245 Interest cost 3 4 10
In FY24 to FY26 the company reported ₹74 crore of profit. Its operating cash flow was about minus ₹5 crore. Management's explanation is that billing is tied to work stages and that cash arrives later. The cash flow statement itself shows only that cash lagged profit.
Debtor days show how many days customers take to pay. The company took an average of 245 days. That figure is partly distorted because 63% of the year's sales came in the last quarter. Unpaid bills at March 2026 were about ₹337 crore, which is about the size of the March quarter's sales (₹319 crore). That is still a long wait. Management says it collected more than ₹40 crore of the June-end bills in July 2026 and no client has delayed payment.
The company also raised ₹20 crore of secured debentures (loans sold to investors and backed by company assets) on 21 May 2026. They carry a 12% interest rate and fall due in May 2028. Management said earlier that it arranged a debenture facility in December and January as a back-up while a bank raised its limit. A 12% rate is high next to bank loans. My reading is that it points to tight cash, but the company has not said so.
Who runs it
The three promoters (the founding owners who run the company) are one family: father, son and daughter-in-law. Nikesh's wife, Reema Choksi, is a non-executive director.
Name Age Role Background ------------ Nikesh K. Choksi 62 Chairman and managing director 40+ years in power. GETCO 21+ years, Torrent Power 3 years, Adani Transmission 8+ years Richi N. Choksi 35 Whole-time director, co-founder (2014) 15+ years in power. Larsen & Toubro 3+ years Priyanka R. Choksi 36 Whole-time director MBA in finance. Chief financial officer from 2014. On the board since August 2024. An interior designer by profession, she also oversees the real-estate arm
(Ages from the FY26 annual report and public sources. Experience from the company's investor presentation.)
Promoter holding: 70.8% in June 2026. It fell from 73.4% in September 2024 to 70.3% in March 2025, after the share issue below. It has risen a little since then.
Small purchases by the promoters. Priyanka and Richi Choksi bought 8,742 and 2,101 shares in the open market in June 2026. Priyanka bought another 2,490 in September. In all, about 13,000 shares, or about ₹1 crore. On the August call, management also hinted at "investment from the promoters and promoter group". It gave no details.
Dealings with the promoters' own company. Viviana Life Spaces is owned 95% by Priyanka Choksi and 5% by Richi Choksi. The listed company paid it advances for capital spending of ₹22.55 crore in FY26 and ₹13.53 crore from April to 3 September 2026. At the 29 September 2026 meeting, shareholders approved up to another ₹50 crore for FY27, to buy office space from it. The ceiling alone is about 44% of the company's net worth. Shareholders approved the proposal, and the voting filing shows that the promoters had an interest in the transaction. The ₹50 crore is a ceiling that shareholders approved, not money already paid. The ₹36 crore paid so far is already nearly a third of net worth. This is the point that most needs a follow-up question.
Who else owns the stock
No mutual fund or institutional investor is a disclosed large holder. - Domestic institutions hold 0.41% (June 2026), up from 0.03% in March 2026. Foreign investors hold about 0%. - The number of shareholders rose from 465 (September 2022) to 4,218 (June 2026). - Exchange bulk-deal data shows only small bulk deals from 2022 and 2023. Nothing from a marquee investor. - Management says it has begun meetings with mutual funds, portfolio managers and family offices. It had investor meets with PL Capital and Arihant Capital on 21 September 2026. It says it will announce any deal.
Money raised, and money that may be coming
When What Details --------- Sep 2024 Preferential issue 3,06,500 shares at ₹625 each (₹19.16 crore) to 56 investors. Shareholders approved on 12 July 2024. About 5% more shares. The price is now 24% above that issue price. Sep 2024 to Jul 2025 Warrants to the promoter (a warrant is a right to buy shares later at a fixed price) 51,500 warrants at ₹625, with 25% paid up front. The promoter paid the other 75% and the warrants became shares on 24 July 2025. Dec 2025 – Jan 2026 Debenture facility Back-up while the bank raised its limit May 2026 ₹20 crore secured debentures 12% interest, due May 2028 Planned Not announced In August, management was asked whether it might raise money through a QIP (a sale of new shares to large institutions) or by selling a stake. It did not rule either out and said it would announce any investment by the promoter group
What to check before buying
- Cash flow. Does operating cash flow turn positive in FY27? Look for the March 2027 numbers. - Related-party advances. How much of the ₹50 crore is paid, and when does the office space arrive? - Orders. Do the "lowest bidder" results become signed orders? Does the first-half ₹500 to 600 crore target get met? - Client concentration. Almost all orders come from Gujarat power companies. A delay or dispute there hits revenue quickly. - Back-ended sales. A big share of the year's revenue lands in one quarter. A slip in that quarter moves the whole year. - Thin trading. A small market cap, few institutions and about 4,200 shareholders mean prices can move sharply. - Plan changes. The real-estate plan reversed within two months. Watch whether the transformer plan stays on schedule. - Pledged shares. Check the latest shareholding pattern on the exchange site for any promoter pledge.
Note: I am not a SEBI-registered investment advisor. This article is for educational purposes only and is not investment advice. Please consult a registered financial advisor before making investment decisions.
Sources
- https://nsearchives.nseindia.com/corporate/VIVIANA15062026143103ilovepdfmerged.pdf (investor presentation, June 2026) - https://nsearchives.nseindia.com/corporate/VIVIANA06082026122633INVESTORPRESENTATION06082026RE.pdf (investor presentation, August 2026) - https://nsearchives.nseindia.com/corporate/VIVIANA13082026123553TRANSCRIPT06082026NSE.pdf (Q1 FY27 call transcript) - https://nsearchives.nseindia.com/corporate/VIVIANA11122025214551TRANSCRIPTNSE04122025.pdf (H1 FY26 call transcript) - https://nsearchives.nseindia.com/content/debt/WDM/VIVIANA05092026162632ANNUALREPORTVIVIANANSE.pdf (annual report FY26) - https://nsearchives.nseindia.com/corporate/VIVIANA21052026115333OUTCOMEOFBM21052026.pdf (debenture allotment) - https://nsearchives.nseindia.com/corporate/VIVIANA04092024221229ALLOTMENTOFEQUITYSHARES04092024.pdf and https://nsearchives.nseindia.com/corporate/VIVIANA04092024221450ALLOTMENTOFWARRANTS04092024.pdf (2024 preferential issue) - https://nsearchives.nseindia.com/corporate/VIVIANA19062026150934SASTDISCLOSURENSE19062026.pdf and https://nsearchives.nseindia.com/corporate/VIVIANA19092026162735SASTDISCLOSURENSE19092026.pdf (promoter purchases) - https://nsearchives.nseindia.com/corporate/VIVIANA30092026232105SCRUTINIZERREPORTNSE.pdf (AGM voting results) - https://www.nseindia.com/get-quote/equity/VIVIANA/Viviana-Power-Tech-Limited (company announcements list, July to October 2026) - https://www.businesstoday.in/amp/latest/economy/story/centre-targets-rs-915-lakh-crore-investment-opportunity-in-transmission-sector-by-2032-450046-2024-10-15 (transmission plan) - https://www.impriindia.com/?p=75834 (distribution scheme)